The Restoration Project
Components:
Phase 1. Restoration & Outside Display
1. Asbestos Removal ..........................
2. Locomotive & Tender Restoration
3. Build Display
a. Fence
..........................................
b. Replica of 1890s
Duncan Depot
c. Water column
.............................
4. Move Locomotive ..........................
5. Canopy to cover locomotive ..........
6. Caboose display
a. Ties, Track and
Ballast ...........
b. Painting of
Caboose .................
|
|
Progress
Completed....................
In Progress...................
......................................
98% completed.............
Flooring.........................
... not budgeted yet...
Completed.....................
.......................................
Completed.....................
... not budgeted yet...
Totals: |
|
Paid
$ 29,000
..................
..................
$ 107,000
.................
$ 8,500
..................
$ 900
$ 145,400
|
|
Committed
$ 10,500.......
$ 20,000
$ 1,000
.....................
.....................
$ 31,500 |
|
Funds
required to be raised for completion:
$ 24,500
$ 5,000
$ 30,000
$ 59,500 |
|